Update from the developers at the Coxhill site – w/c 20/02 and 27/02

Works in week commencing 20/02/2023

  • Block & beam plots 3-6
  • Sub-structure Blockwork plot 11
  • Drainage connections plots 7-10
  • Muck away
  • Scaffolding to plots 1-6

Works week commencing 27th February 2023
  • Block & beam plots 7-10
  • Sub-structure Blockwork plot 12
  • Drainage connections plots 11
  • Muck away
  • Scaffolding to plots 3-6