Update on works undertaken this week and planned works for next week
Works week commencing 13/2/2023
- Block & Beam floor plots 1 & 2
- Foul water manhole ready for sewer connection
- Sub-Blockwork to plots 3-10
- Footings to plot 11
- Drainage connections from plot 1-6 into the main run
- Muck away
Works wc 20/2/2023
- Block & beam plots 3-6
- Sub-structure Blockwork plot 11
- Drainage connections plots 7-10
- Muck away
- Scaffolding to plots 1-6
Derek Amas MCIOB
Senior Site Manager