Latest update from the developers at the Coxhill site

Update on works undertaken this week and planned works for next week

Works week commencing 13/2/2023

  • Block & Beam floor plots 1 & 2
  • Foul water manhole ready for sewer connection
  • Sub-Blockwork to plots 3-10
  • Footings to plot 11
  • Drainage connections from plot 1-6 into the main run
  • Muck away

Works wc 20/2/2023

  • Block & beam plots 3-6
  • Sub-structure Blockwork plot 11
  • Drainage connections plots 7-10
  • Muck away
  • Scaffolding to plots 1-6

Derek Amas MCIOB

Senior Site Manager