This week’s work

  • We have installed the tarmac base layer to the development road which now gives us a clean base to work from
  • Foundations for plots 1-6 have been excavated and filled with concrete ready for bricklayers to commence
  • We have commenced removal of surplus risings from the road & foundation digs and this will continue throughout the next few weeks

Works for next week

  • Continuation of muck away from site
  • Continuation of footing excavation at top end of site
  • Commencement of sub structure blockwork