The following information has been provided by W W Martin on the development at Coxhill which they are managing:
This week’s work
- We have installed the tarmac base layer to the development road which now gives us a clean base to work from
- Foundations for plots 1-6 have been excavated and filled with concrete ready for bricklayers to commence
- We have commenced removal of surplus risings from the road & foundation digs and this will continue throughout the next few weeks
Works for next week
- Continuation of muck away from site
- Continuation of footing excavation at top end of site
- Commencement of sub structure blockwork
- Installation of block & beam floor ready for timber frame