The Senior Site Manager for this development, Mr Derek Amas, MCIOB, has provided the following update:
Throughout this this week we have undertaken the following :
- Removal of Hedgerow stumps & Bank to new entrance
- Commence cut of new entrance road
- Continuation of Topsoil strip
- Completion of PROW footpath
- Capping of buffer zone with topsoil
- Continuation of hedge trimming and stump removal
- Continuation of topsoil stripping
- Continuation of road cutting
- Muck away
- Cutting back of bank for visibility splay
- Water run off mitigation